It is known to us that our Project-Management study materials are enjoying a good reputation all over the world. Our study materials have been approved by thousands of candidates. You may have some doubts about our product or you may suspect the pass rate of it, but we will tell you clearly, it is totally unnecessary. If you still do not trust us, you can choose to download demo of our Project-Management Test Torrent. The high quality and the perfect service system after sale of our Project-Management exam questions have been approbated by our local and international customers. So you can rest assured to buy.
Topic | Details |
---|---|
Topic 1 |
|
Topic 2 |
|
Topic 3 |
|
Topic 4 |
|
Topic 5 |
|
>> Valid Project-Management Exam Discount <<
We have compiled the Project-Management test guide for these candidates who are trouble in this exam, in order help they pass it easily, and we deeply believe that our Project-Management exam questions can help you solve your problem. Believe it or not, if you buy our study materials and take it seriously consideration, we can promise that you will easily get the certification that you have always dreamed of. We believe that you will never regret to buy and practice our Project-Management latest question as the high pass rate of our Project-Management exam questions is 99% to 100%.
NEW QUESTION # 35
During the CD phase, it is discovered that the owner's food service consultant made a mistake that results in the owner asking the architect to revise the design.
How should the architect proceed?
Answer: A
Explanation:
Comprehensive Detailed Explanation:
If the owner's food service consultant made an error and the architect is asked to revise the design to address it, that request falls outside the architect's basic services and is considered an Additional Service. Per AIA B101, the architect should submit a formal request for additional services, outlining the scope and cost of the requested changes.
References:
AIA B101 Article 4 - Additional Services
NCARB ARE 5.0 Handbook - Scope changes and managing consultant errors
NEW QUESTION # 36
Which four factors will most affect the choice of project delivery method? Check the four that apply.
Answer: A,B,C,E
Explanation:
A). Project scope: Impacts complexity and integration needs.
C). Owner capabilities: Determines whether the owner can manage multiple contracts (as in DBB or CM).
E). Risk tolerance: Risk-averse owners may prefer DB or CM-at-risk with cost guarantees.
F). Construction cost: Influences whether fast-tracking or GMP methods are needed.
Incorrect:
B). The firm's size is rarely a determining factor.
D). Code compliance is required in all methods but doesn't drive delivery choice.
References:
AHPP Chapter 10 - Choosing a Delivery Method
NCARB ARE 5.0 Handbook - Delivery Method Evaluation Criteria
NEW QUESTION # 37
Which of the following best describes a construction manager (CM) at risk?
Answer: D
Explanation:
A CM at risk (CMc) is both an advisor during design and the constructor during the construction phase. A defining characteristic is the Guaranteed Maximum Price (GMP), placing financial risk on the CM for cost overruns beyond the GMP.
Incorrect options:
B and D describe CM as Advisor (CMa), not CMc.
C is too vague and lacks the critical GMP element.
References:
AIA CMc Contracts: A133 and A134
AHPP, 15th ed., Chapter 10: Project Delivery Methods
NCARB ARE 5.0 Handbook - Delivery Methods Overview
NEW QUESTION # 38
Design Firm ABC is awarded two projects, but they do not have enough staff to support the execution of both projects due to unexpected staffing issues. ABC is deciding if they need to hire staff from an outside firm to execute the projects.
Which one of the following sets of staff members would adequately support ABC's staffing needs?
Answer: A
Explanation:
Comprehensive Detailed Explanation:
From the schedule:
Total lead architect hours needed = 16 + 24 = 40 hrs/week
Firm ABC only has 50% of 1 Lead Architect = 20 hrs/week # Needs 20 hrs more Total drafter hours needed = 80 + 80 = 160 hrs/week Firm ABC has 3 Drafters at 100% = 3 × 40 = 120 hrs/week # Needs 40 hrs more Thus, the firm needs 1 Lead Architect (for 20 hrs) and 1 Drafter (for 40 hrs) from the augmenting firm to meet the requirement.
References:
NCARB ARE 5.0 PjM Handbook - Staffing plans and workload balancing
NEW QUESTION # 39
Which of the following is a key advantage of using Building Information Modeling (BIM)?
Answer: D
Explanation:
BIM facilitates integrated coordination of multiple disciplines by enabling a shared digital model, reducing conflicts, improving visualization, and enhancing collaboration. It supports clash detection and improves efficiency but does not eliminate construction documents or replace contractors. ARE 5.0 PjM emphasizes technology's role in project delivery.
NEW QUESTION # 40
......
Are you still feeling uncomfortable about giving up a lot of time to entertain, work or accompany your family and friends in preparation for the exam? Using Project-Management Quiz torrent, you can spend less time and effort reviewing and preparing, which will help you save a lot of time and energy. When some candidates trying to overcome an exam, they will all first think of choosing a good study material to prepare for their exam. The ARE 5.0 Project Management (PjM) Exam prep torrent has a variety of self-learning and self-assessment functions to test learning outcome, which will help you increase confidence to pass exam.
Project-Management Valid Test Pattern: https://www.actual4exams.com/Project-Management-valid-dump.html